Roughly how long will it take to produce our new hardware product?

May 6, 2026

Manish Agrahari

This is a really difficult question to answer as every new product launch project is different, however, we’ll try to give you some ballpark figures.

  • Engineering design: 15 days to 6 months
  • Accelerated life testing on prototypes and iterations until a final approved prototype: 1 to 3 months
  • Tooling fabrication: often around 6 weeks
  • Pre-production preparation, including pilot run(s): 1 to 3 months
  • Mass production (first batch): 1 to 3 months

Note: we typically help clients after the industrial design has been completed.

Category:For new/customized products